Construction progress update

Construction progress update

Here’s a look at progress through mid-January on completion of major construction elements for the new Pensacola Bay Bridge.

Test and production piles driven: 1,450 of 2,124 (all piles for the eastbound structure)

Trophy pieces set: 193 of 416

Beams (girders) set: 420 of 1,020

Bridge decks poured: 77 of 210

When the new eastbound bridge is complete, two lanes of eastbound and two lanes of westbound traffic will be temporarily transitioned to this new bridge. Crews will then demolish the existing bridge and construct the new westbound structure, along with a new element of work that has been added to the project, the reconstruction of the U.S. 98/17th Avenue interchange in Pensacola.

All construction work is currently estimated for completion in mid-2021.

Top
Skip to toolbar