Construction progress update

Construction progress update

Here’s a look at progress through mid-March on completion of major construction elements for the new Pensacola Bay Bridge.

Test and production piles driven: 1,453 of 2,124

Trophy pieces set: 216 of 416 (all trophy pieces for the eastbound structure and 8 for westbound)

Beams (girders) set: 475 of 1,020

Bridge decks poured: 83 of 210

Bridge construction, as well as re-construction of the 17th Avenue interchange, is currently estimated for completion in mid-2021.